Text File  |  1993-04-11  |  20KB  |  624 lines

  1. "6_2_3_21_2.TXT" (19142 bytes) was created on 12-30-88
  2.  
  3. SPACE SHUTTLE CHRONOLOGY 1972-1979
  4.  
  5. 1972
  6.  
  7. Aug. 9  Rockwell receives authority to proceed, space shuttle orbiter
  8.  
  9. 1974
  10.  
  11. June 4  Start structural assembly crew module, Enterprise (OV-101)
  12.  
  13. July 17 Start long-lead fabrication (MPTA-098)
  14.  
  15. Aug. 26 Start structural assembly aft fuselage, Enterprise (OV-101)
  16.  
  17. 1975
  18.  
  19. Jan. 6  Start long-lead fabrication aft fuselage (STA-099)
  20.  
  21. March 27        Midfuselage on dock, Palmdale, Enterprise (OV-101)
  22.  
  23. March 27        Start long-lead fabrication aft fuselage, Columbia (OV-102)
  24.  
  25. May 23  Wings on dock, Palmdale-less elevons, seals and main gear
  26. doors-Enterprise (OV-101)
  27.  
  28. May 27  Vertical stabilizer on dock, Palmdale (main fin box only),
  29. Enterprise (OV-101)
  30.  
  31. June 24 Start structural assembly (MPTA-098)
  32.  
  33. Aug. 25 Start final assembly and closeout system installation,
  34. Enterprise (OV-101)
  35.  
  36. Sept. 5 Aft fuselage on dock, Palmdale, Enterprise (OV-101)
  37.  
  38. Oct. 17 Space shuttle main engine first main stage test at NSTL
  39.  
  40. Oct. 31 Lower forward fuselage on dock, Palmdale, Enterprise (OV-101)
  41.  
  42. Nov. 17 Start long-lead fabrication of crew module, Columbia (OV-102)
  43.  
  44. Dec. 1  Upper forward fuselage on dock, Palmdale, Enterprise (OV-101)
  45.  
  46. Dec. 20 First SSME 60-second duration test, NSTL
  47.  
  48. Dec. 31 1/4-scale model ground vibration test facility construction
  49. complete, Downey, Building 288
  50.  
  51. 1976
  52.  
  53. Jan. 16 Crew module on dock, Palmdale, Enterprise (OV-101)
  54.  
  55. Jan. 23 MPTA-098 truss on dock, Downey
  56.  
  57. Feb. 16 Start fabrication forward fuselage (STA-099)
  58.  
  59. March 3 Payload bay doors on dock, Palmdale, Enterprise (OV-101)
  60.  
  61. March 12        Complete final assembly and closeout system installation,
  62. Palmdale, Enterprise (OV-101)
  63.  
  64. March 15        Start functional checkout, Enterprise (OV-101)
  65.  
  66. March 17        Complete premate MPTA test structure, Downey, and deliver to
  67. Palmdale
  68.  
  69. April 2 Crew escape system test sled on dock, Downey
  70.  
  71. April 3 Complete assembly and deliver MPTA structure on dock,
  72. Lockheed test site, Palmdale
  73.  
  74. April 22        Body flap on dock, Palmdale, Enterprise (OV-101)
  75.  
  76. May 3   Complete MPTA-098 proof load test setup, Lockheed test site,
  77. Palmdale
  78.  
  79. June 14 Start aft fuselage assembly (STA-099)
  80.  
  81. June 24 Complete MPTA-098 proof load test, Lockheed test site and on
  82. dock, Palmdale
  83.  
  84. June 25 Complete functional checkout, Enterprise (OV-101)
  85.  
  86. June 28 Start assembly of crew module, Columbia (OV-102)
  87.  
  88. June 28 Start horizontal ground vibration tests and proof load tests,
  89. Enterprise (OV-101)
  90.  
  91. June 29 MPTA-098 truss assembly, Palmdale, Building 294 to Building
  92. 295
  93.  
  94. June 30 SSME dummy set on dock, Palmdale, Enterprise (OV-101)
  95.  
  96. July 8  MPTA-098 on dock, Downey, without truss assembly
  97.  
  98. July 12 Start installation secondary structure (MPTA-098)
  99.  
  100. Aug. 2  Start final assembly forward fuselage (STA-099)
  101.  
  102. Aug. 2  Start carrier aircraft modification
  103.  
  104. Aug. 20 Complete horizontal ground vibration tests and proof load
  105. tests, Enterprise (OV-101)
  106.  
  107. Aug. 23 Start Delta F modification, Enterprise (OV-101)
  108.  
  109. Aug. 27 Reaction control system/orbital maneuvering system pods
  110. (simulated), approach and landing tests, on dock, Palmdale,
  111. Enterprise (OV-101)
  112.  
  113. Aug.    Start overland roadway construction from Palmdale to Edwards Air
  114. Force Base
  115.  
  116. Sept. 10        Complete Delta F modifications, Enterprise (OV-101)
  117.  
  118. Sept. 13        Start preparations for first rollout, Enterprise (OV-101)
  119.  
  120. Sept. 13        Start assembly aft fuselage, Columbia (OV-102)
  121.  
  122. Sept. 17        Rollout Enterprise (OV-101)
  123.  
  124. Sept. 17        Complete on-stand construction, NSTL
  125.  
  126. Sept. 20        Start Delta F retest, Enterprise (OV-101)
  127.  
  128. Oct. 1  Start final assembly, vertical stabilizer (STA-099)
  129.  
  130. Oct. 1  Start final assembly, wing (STA-099)
  131.  
  132. Oct. 15 Midfuselage on dock, Palmdale (STA-099)
  133.  
  134. Oct. 26 Escape system test assembly sled ship from Downey to
  135. Holloman, N.M.
  136.  
  137. Oct. 29 Deliver ejection seats, Enterprise (OV-101)
  138.  
  139. Oct. 29 Complete Delta F retest, Enterprise (OV-101)
  140.  
  141. Oct. 31 Solid rocket booster 1/4-scale model (burnout configuration)
  142. on dock, Downey
  143.  
  144. Nov. 4  Complete 747 shuttle carrier aircraft modification, rollout,
  145. Boeing
  146.  
  147. Nov. 18 Start escape system sled test, Holloman, N.M.
  148.  
  149. Nov. 26 Complete integrated checkout, Enterprise (OV-101)
  150.  
  151. Nov. 28 Complete orbiter transporter strongback
  152.  
  153. Dec. 7  Tail cone fairing on dock, Palmdale
  154.  
  155. Dec. 10 Complete overland roadway construction, Palmdale to Edwards
  156. Air Force Base
  157.  
  158. Dec. 13 Start assembly upper forward fuselage, Columbia (OV-102)
  159.  
  160. Dec. 17 External tank 1/4-scale model on dock, Downey
  161.  
  162. 1977
  163.  
  164. Jan. 3  Start assembly vertical stabilizer, Columbia (OV-102)
  165.  
  166. Jan. 14 Complete postcheckout, Enterprise (OV-101)
  167.  
  168. Jan. 14 Boeing 747 shuttle carrier aircraft delivered to DFRF
  169.  
  170. Jan. 25 Complete aft fuselage assembly on dock, Palmdale (STA-099)
  171.  
  172. Jan. 28 Simulated crew module on dock, Palmdale (STA-099)
  173.  
  174. Jan. 31 SRB 1/4-scale model (lift-off configuration) on dock, Downey
  175.  
  176. Jan. 31 Enterprise (OV-101) transported overland from Palmdale to
  177. DFRF (36 miles)
  178.  
  179. Jan. 31 Mass simulated SSMEs on dock, Palmdale, Enterprise (OV-101)
  180.  
  181. Feb. 7  Enterprise (OV-101)/shuttle carrier aircraft mate start
  182.  
  183. Feb. 10 Midfuselage on dock, Palmdale, Columbia (OV-102)
  184.  
  185. Feb. 15 Complete Enterprise (OV-101)/shuttle carrier aircraft mated
  186. ground vibration test and taxi tests
  187.  
  188. Feb. 18 Conduct first inert captive flight, DFRF (2 hours, 5
  189. minutes), Enterprise (OV-101)
  190.  
  191. Feb. 22 Conduct second inert captive flight, DFRF (3 hours, 13
  192. minutes), Enterprise (OV-101)
  193.  
  194. Feb. 25 Conduct third inert captive flight, DFRF (2 hours, 28
  195. minutes), Enterprise (OV-101)
  196.  
  197. Feb. 28 Conduct fourth inert captive flight, DFRF (2 hours, 11
  198. minutes), Enterprise (OV-101)
  199.  
  200. March 2 Conduct fifth inert captive flight, DFRF (1 hour, 39
  201. minutes), Enterprise (OV-101)
  202.  
  203. March 16        Wings on dock, Palmdale (STA-099)
  204.  
  205. March 21        Orbiter 1/4-scale model on dock, Downey
  206.  
  207. April 1 Lower forward fuselage on dock, Palmdale (STA-099)
  208.  
  209. April 6 Upper forward fuselage on dock, Palmdale (STA-099)
  210.  
  211. April 6 Vertical stabilizer on dock, Palmdale (STA-099)
  212.  
  213. May 20  Nose landing gear doors on dock, Palmdale (STA-099)
  214.  
  215. May 26  Aft payload bay doors on dock, Palmdale (STA-099)
  216.  
  217. May 27  Complete systems installation/final acceptance, MPTA-098,
  218. transport from Downey to Seal Beach
  219.  
  220. May 31  SRB 1/4-scale model, burnout and maximum q configuration, on
  221. dock, Downey
  222.  
  223. May 31  SRB 1/4-scale model, lift-off configuration, on dock, Downey
  224.  
  225. May 31  Body flap on dock, Palmdale (STA-099)
  226.  
  227. June 3  Ship MPTA-098 from Seal Beach, Calif., to NSTL
  228.  
  229. June 7  Complete integrated checkout and hot-fire ground test, DFRF,
  230. Enterprise (OV-101)
  231.  
  232. June 18 Conduct first manned captive active flight, Enterprise
  233. (OV-101)/shuttle carrier aircraft, DFRF (55 minutes, 46 seconds)
  234.  
  235. June 23 Deliver first SSME to NSTL (MPTA-098)
  236.  
  237. June 24 Deliver MPTA-098 to NSTL
  238.  
  239. June 28 Conduct second manned captive active flight, Enterprise
  240. (OV-101)/shuttle carrier aircraft, DFRF (1 hour, 2 minutes)
  241.  
  242. July 5  Start long-lead fabrication aft fuselage, Discovery (OV-103)
  243.  
  244. July 8  Deliver second main engine to NSTL (MPTA-098)
  245.  
  246. July 14 Deliver third main engine to NSTL (MPTA-098)
  247.  
  248. July 18 Conduct 2-minute firing of SRB at Brigham City, Utah, Thiokol
  249. (2.4 million pounds of thrust)
  250.  
  251. July 22 Deliver forward payload bay doors, on dock, Palmdale (STA-099)
  252.  
  253. July 26 Conduct third manned captive active flight, Enterprise
  254. (OV-101)/shuttle carrier aircraft, DFRF (59 minutes, 50 seconds)
  255.  
  256. Aug. 12 Conduct first free flight, ALT, tail cone on, DFRF (5
  257. minutes, 21 seconds), Enterprise (OV-101), lake bed Runway 17
  258.  
  259. Aug. 26 Deliver wings on dock, Palmdale, Columbia (OV-102)
  260.  
  261. Sept. 7 Lower forward fuselage on dock, Palmdale, Columbia (OV-102)
  262.  
  263. Sept. 10        Deliver external tank MPTA-098 (Martin Marietta) to NSTL
  264.  
  265. Sept. 13        Conduct second free flight, ALT, tail cone on, DFRF (5
  266. minutes, 28 seconds), Enterprise (OV-101), lake bed Runway 17
  267.  
  268. Sept. 23        Conduct third free flight, ALT, tail cone on, DFRF (5
  269. minutes, 34 seconds), Enterprise (OV-101), lake bed Runway 15
  270.  
  271. Sept. 30        Complete mate vertical stabilizer, Palmdale (STA-099)
  272.  
  273. Oct. 12 Conduct fourth free flight, ALT, first tail cone off, DFRF (2
  274. minutes, 34 seconds), Enterprise (OV-101), lake bed Runway 17
  275.  
  276. Oct. 26 Conduct fifth free flight, ALT, final tail cone off, DFRF (2
  277. minutes, 1 second), Enterprise (OV-101), concrete Runway 04
  278.  
  279. Oct. 28 Lower forward fuselage on dock, Palmdale, Columbia (OV-102)
  280.  
  281. Nov. 4  Start forward reaction control system development tests, White
  282. Sands Test Facility, N.M.
  283.  
  284. Nov. 4  Deliver aft fuselage on dock, Palmdale, Columbia (OV-102)
  285.  
  286. Nov. 7  Forward RCS on dock, Palmdale (STA-099)
  287.  
  288. Nov. 7  Start final assembly and closeout system installation,
  289. Palmdale, Columbia (OV-102)
  290.  
  291. Nov. 15 First ferry flight test, DFRF (3 hours, 21 minutes),
  292. Enterprise (OV-101)
  293.  
  294. Nov. 16 Second ferry flight test, DFRF (4 hours, 17 minutes),
  295. Enterprise (OV-101)
  296.  
  297. Nov. 17 Third ferry flight test, DFRF (4 hours, 13 minutes),
  298. Enterprise (OV-101)
  299.  
  300. Nov. 18 Fourth ferry flight test, DFRF (3 hours, 37 minutes),
  301. Enterprise (OV-101)
  302.  
  303. Dec. 9  Complete approach and landing flight tests, including ferry
  304. flights, Enterprise (OV-101)
  305.  
  306. Dec. 12 Start removal for mated vertical ground vibration test
  307. modification at DFRF, Enterprise (OV-101)
  308.  
  309. Dec. 13 Complete propellant load testing, NSTL (MPTA-098)
  310.  
  311. Dec. 31 Deliver SSME envelope/electrical simulators on dock,
  312. Palmdale, Columbia (OV-102)
  313.  
  314. 1978
  315.  
  316. Jan. 10 Vertical stabilizer on dock, Palmdale, Columbia (OV-102)
  317.  
  318. Jan. 18 Second SRB firing, Thiokol
  319.  
  320. Feb. 10 Complete final assembly, STA-099, Palmdale
  321.  
  322. Feb. 14 STA-099 on dock, Lockheed facility, Palmdale
  323.  
  324. Feb. 17 Crew module on dock, Palmdale, Columbia (OV-102)
  325.  
  326. Feb. 24 Body flap on dock, Palmdale, Columbia (OV-102)
  327.  
  328. March 3 Complete modification for mated vertical ground vibration
  329. test, DFRF, Enterprise (OV-101)
  330.  
  331. March 6 Upper forward fuselage on dock, Palmdale, Columbia (OV-102)
  332.  
  333. March 10        Ferry Enterprise (OV-101) atop shuttle carrier aircraft from
  334. DFRF to Ellington Air Force Base, Texas (approximately 3 hours, 38
  335. minutes)
  336.  
  337. March 13        Ferry Enterprise (OV-101) atop shuttle carrier aircraft from
  338. Ellington AFB to Marshall Space Flight Center, Huntsville, Ala.
  339. (approximately 2 hours)
  340.  
  341. March 19        Aft payload bay doors on dock, Palmdale, Columbia (OV-102)
  342.  
  343. March 31        External tank for mated vertical ground vibration tests
  344. arrives at MSFC from Martin Marietta, Michoud, La.
  345.  
  346. March 31        Operational readiness date, solid rocket booster
  347. refurbishment and subassembly, Kennedy Space Center, Fla.
  348.  
  349. April 14        Complete ground vibration test modification at MSFC; deliver
  350. Enterprise (OV-101) for mated vertical ground vibration test
  351.  
  352. April 21        First static firing, MPTA-098, NSTL (2.5 seconds; stub
  353. nozzles)
  354.  
  355. April 23        Complete final assembly and closeout system installation,
  356. ready for power-on, Columbia (OV-102)
  357.  
  358. April 24        Start precombined systems test, Columbia (OV-102)
  359.  
  360. April 28        Forward payload bay doors on dock, Palmdale, Columbia
  361. (OV-102)
  362.  
  363. May 19  Second static firing MPTA-098, NSTL (15 seconds, 70% thrust;
  364. stub nozzles)
  365.  
  366. May 19  Start forward RCS thermal tests, WSTF
  367.  
  368. May 26  Start development test aft RCS, WSTF
  369.  
  370. May 26  Complete forward RCS structure, Columbia (OV-102)
  371.  
  372. May 26  Upper forward fuselage mate, Columbia (OV-102)
  373.  
  374. May 30  Start Enterprise (OV-101)/ ET mated vertical ground vibration
  375. test, MSFC
  376.  
  377. May 31  Loaded SRBs (2) arrive at MSFC for mated vertical ground
  378. vibration test
  379.  
  380. June 15 Third static firing, MPTA-098, NSTL (50 seconds, 90% thrust,
  381. last 5 seconds 70% thrust; stub nozzles)
  382.  
  383. July 3  Deliver left-hand OMS/RCS pod to WSTF
  384.  
  385. July 7  Fourth static firing, MPTA-098, NSTL (No. 2 engine 70% thrust
  386. for 90 seconds, simulated one engine out at 90 seconds, then No. 1
  387. and No. 3 to 90% thrust-then to 70% thrust, then to 90% for 100
  388. seconds; stub nozzles)
  389.  
  390. July 7  Complete mate forward and aft payload bay doors, Columbia
  391. (OV-102)
  392.  
  393. July 13 Complete forward RCS development tests, WSTF
  394.  
  395. July 13 Reconfigure from boost to launch, mated vertical ground
  396. vibration test, MSFC, Enterprise (OV-101)
  397.  
  398. July 15 Deliver SRBs (2) empty to MSFC for mated vertical ground
  399. vibration test
  400.  
  401. July 21 First firing development test, OMS, WSTF
  402.  
  403. July 31 Operational readiness date, Orbiter Processing Facility Bay
  404. 1, shuttle landing facility, and Hypergolic Maintenance Facility, KSC
  405.  
  406. Aug. 11 Complete forward RCS, Columbia (OV-102)
  407.  
  408. Aug. 11 Complete test preparation, STA-099, Lockheed facility,
  409. Palmdale
  410.  
  411. Aug. 11 Complete forward RCS thermal test, WSTF
  412.  
  413. Aug. 14 Start coefficient tests, STA-099, Lockheed facility, Palmdale
  414.  
  415. Aug. 31 Operational readiness date, Vertical Assembly Building High
  416. Bays 3 and 4, KSC
  417.  
  418. Sept. 8 Start OMS left-hand development test, WSTF
  419.  
  420. Sept. 20        Start launch configuration test lift-off configuration,
  421. Enterprise (OV-101)/ ET/SRBs mated vertical ground vibration test at
  422. MSFC
  423.  
  424. Sept. 20        Start acoustic test, forward RCS, WSTF
  425.  
  426. Sept. 25        Start precombined system test, Columbia (OV-102)
  427.  
  428. Sept. 29        Complete coefficient tests, STA-099, Lockheed facility,
  429. Palmdale
  430.  
  431. Sept. 30        Operational readiness date, mobile launcher platform, KSC
  432.  
  433. Oct. 19 Third SRB firing, Thiokol
  434.  
  435. Nov. 11 Complete forward RCS acoustic test, WSTF
  436.  
  437. Nov. 15 Complete OMS development test
  438.  
  439. Nov. 15 Complete aft RCS development test, WSTF
  440.  
  441. Nov. 30 Operational readiness date, Pad A, KSC
  442.  
  443. Dec. 9  Start OMS Phase I qualification tests, WSTF
  444.  
  445. Dec. 15 Start aft RCS Phase I qualification tests, WSTF
  446.  
  447. Dec. 15 Complete precombined system test, Palmdale, Columbia (OV-102)
  448.  
  449. 1979
  450.  
  451. Jan. 2  Start long-lead fabrication crew module, Challenger (OV-099)
  452.  
  453. Jan. 30 Start orbiter/ET/SRB burnout mated vertical ground vibration
  454. test, MSFC
  455.  
  456. Jan. 31 Deliver shuttle carrier aircraft to DFRF for ferry operations
  457.  
  458. Jan. 31 Start left-hand OMS Phase I qualification test, WSTF
  459.  
  460. Jan. 31 Mission Control Center-Houston/Goldstone ready for
  461. operational flight test early operations
  462.  
  463. Feb. 3  Complete combined systems test, Palmdale, Columbia (OV-102)
  464.  
  465. Feb. 16 Airlock on dock, Palmdale, Columbia (OV-102)
  466.  
  467. Feb. 17 Fourth SRB firing, Thiokol
  468.  
  469. Feb. 26 Complete mated vertical ground vibration test program at
  470. MSFC, Enterprise (OV-101)
  471.  
  472. Feb. 28 Operational readiness date, shuttle landing site, DFRF
  473. (Edwards AFB) Runway 23, for first manned orbital flight
  474.  
  475. March 5 Complete postcheckout, Palmdale, Columbia (OV-102)
  476.  
  477. March 8 Complete closeout inspection, final acceptance, Palmdale,
  478. Columbia (OV-102)
  479.  
  480. March 8 Columbia (OV-102) transported overland from Palmdale to DFRF
  481. (38 miles)
  482.  
  483. March 9 Shuttle carrier aircraft/Columbia (OV-102) test flight at
  484. NASA DFRF
  485.  
  486. March 17        Space shuttle main engine 2005, first flight engine
  487. delivered to NSTL for acceptance test firings
  488.  
  489. March 20        Ferry flight, shuttle carrier aircraft/Columbia (OV-102)
  490. from DFRF to Biggs Army Air Base, El Paso, Texas (3 hours, 20 minutes)
  491.  
  492. March 22        Ferry flight, shuttle carrier aircraft/Columbia (OV-102)
  493. from Biggs Army Air Base to Kelly AFB, San Antonio, Texas (1 hour, 39
  494. minutes)
  495.  
  496. March 23        Ferry flight, shuttle carrier aircraft/Columbia (OV-102)
  497. from Kelly AFB to Eglin AFB, Fla. (2 hours, 12 minutes)
  498.  
  499. March 24        Ferry flight, shuttle carrier aircraft/Columbia (OV-102)
  500. from Eglin AFB to KSC (1 hour, 33 minutes)
  501.  
  502. March 30        Space shuttle main engine 2007, flight engine delivered to
  503. NSTL for acceptance test firing
  504.  
  505. April 6 Complete Phase I qualification tests, aft RCS, WSTF
  506.  
  507. April 10        Ferry flight, shuttle carrier aircraft/Enterprise (OV-101)
  508. from MSFC to KSC (1 hour, 52 minutes)
  509.  
  510. April 16        Space shuttle main engine 2006, flight engine delivered to
  511. NSTL, for acceptance test firing
  512.  
  513. April 18        Complete left-hand OMS/RCS Phase I qualification, WSTF
  514.  
  515. May 1   Enterprise (OV-101)/ ET/SRBs mated on mobile launcher platform,
  516. transported to Launch Complex 39-A from Vehicle Assembly Building at
  517. KSC
  518.  
  519. May 4   Start forward RCS Phase I qualification tests, WSTF
  520.  
  521. May 4   Fifth static firing, MPTA-098, NSTL, flight nozzles 1.5 seconds
  522.  
  523. May 10  Deliver right-hand OMS/RCS from McDonnell Douglas, St. Louis,
  524. to KSC, Columbia (OV-102)
  525.  
  526. May 15  Deliver left-hand OMS/RCS from McDonnell Douglas to KSC,
  527. Columbia (OV-102)
  528.  
  529. May 30  Deliver ET used in mated vertical ground vibration test from
  530. MSFC to Martin Marietta for refurbishment
  531.  
  532. June 12 Fifth static firing, MPTA-098, NSTL, flight nozzles (54
  533. seconds, early cutoff, accelerometer filters)
  534.  
  535. June 15 First SRB qualification firing, Thiokol, Utah, 122 seconds;
  536. nozzle extension severed at end of run as in actual mission; full
  537. cycle gimbal
  538.  
  539. June 21 Start assembly crew module, Challenger (OV-099)
  540.  
  541. July 2  Sixth static firing, MPTA-098, NSTL, flight nozzles (19
  542. seconds, early cutoff-main fuel valve rupture)
  543.  
  544. July 23 Enterprise (OV-101), ET, SRBs transported on mobile launcher
  545. platform from Launch Complex 39-A to Vehicle Assembly Building at KSC
  546.  
  547. Aug. 1  Start long-lead fabrication crew module, Discovery (OV-103)
  548.  
  549. Aug. 6  Complete limit test (STA-099), Lockheed facility, Palmdale
  550.  
  551. Aug. 10 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  552. KSC to Atlanta (1 hour, 55 minutes)
  553.  
  554. Aug. 11 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  555. Atlanta to St. Louis (1 hour, 50 minutes)
  556.  
  557. Aug. 12 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  558. St. Louis to Tulsa (1 hour, 35 minutes)
  559.  
  560. Aug. 13 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  561. Tulsa to Denver (2 hours)
  562.  
  563. Aug. 14 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  564. Denver to Hill AFB, Ogden, Utah (1 hour, 30 minutes)
  565.  
  566. Aug. 15 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  567. Ogden to Vandenberg AFB (2 hours, 20 minutes)
  568.  
  569. Aug. 16 Ferry flight, shuttle carrier aircraft/Enterprise (OV-101),
  570. Vandenberg AFB to DFRF (1 hour, 10 minutes)
  571.  
  572. Aug. 23 Enterprise (OV-101)/ shuttle carrier demate, DFRF
  573.  
  574. Aug. 27 Start long-lead fabrication crew module, Discovery (OV-103)
  575.  
  576. Aug. 31 Complete OMS Phase II qualification tests, WSTF
  577.  
  578. Aug.    Second SRB qualification firing, Thiokol
  579.  
  580. Sept. 5 Complete forward RCS Phase I qualification tests, WSTF
  581.  
  582. Sept. 12        Start forward RCS Phase II qualification tests, WSTF
  583.  
  584. Sept. 21        Start aft RCS Phase II qualification tests, WSTF
  585.  
  586. Oct. 5  Complete setup and thermal tests (STA-099), Lockheed facility,
  587. Palmdale
  588.  
  589. Oct. 24 Sixth static firing, MPTA-098, NSTL, flight nozzle (scrubbed,
  590. hydrogen detector oversensitive)
  591.  
  592. Oct. 30 Move Enterprise (OV-101) from DFRF overland to Rockwell
  593. Palmdale facility (38 miles)
  594.  
  595. Nov. 2  Start OMS left-hand pod Phase II qualification, WSTF
  596.  
  597. Nov. 3  Complete Columbia (OV-102) auxiliary power unit hot fire
  598. tests, Orbiter Processing Facility, KSC
  599.  
  600. Nov. 4  MPTA-098 static firing, NSTL (10 seconds, flight nozzles, SSME
  601. liquid oxygen turbine, seal cavity pressure, high-cutoff steerhorn
  602. failure)
  603.  
  604. Nov. 7  Deliver STA-099 from Lockheed facility, Palmdale to Rockwell
  605. Palmdale for rework as second operational orbiter (redesignated
  606. Challenger {OV-099})
  607.  
  608. Nov. 12 Complete qualification test OMS engine at WSTF
  609.  
  610. Dec. 7  Demate payload bay door, Palmdale, Challenger (OV-099)
  611.  
  612. Dec. 14 Complete demate body flap, Palmdale, Challenger (OV-099)
  613.  
  614. Dec. 16 Orbiter integrated test start, Columbia (OV-102), KSC
  615.  
  616. Dec. 17 Sixth static firing, MPTA-098, NSTL, 554 seconds (340 seconds
  617. at 100% rated power level, then 90% at 385 seconds, 80% at 450
  618. seconds, 70% at 505 seconds; 1 engine shut down-other 2 continued at
  619. 70% until 554 seconds; pogo and gimbaling tests accomplished; stub
  620. nozzles)
  621.  